More than 25 percent of Cleveland residents either carpool to work or commute via public transit, walking or biking; 11.5 percent of commuters have no access to a vehicle. Given the city’s commitment to sustainability, clean air, and vibrancy and equity in its urban core, Cleveland should consider alternatives built around public transit that include safe routes for pedestrians and cyclists.  

For immediate release
Contact Amanda Woodrum, 330.780.8321
Download statement (1 pg)

Cleveland should consider alternatives

The Federal Highway Administration estimates the cost of building Cleveland’s Opportunity Corridor at $331.3 million, including final design, project administration and management, land acquisition, utility relocation, implementation of environmental commitments and mitigation measures, and construction activities.[1] In making a decision about funding for the Corridor, the Ohio Department of Transportation developed and analyzed four alternatives

Reddit
LinkedIn
Facebook
X
Threads
Email

Get updates to your inbox.